Tecco1

Transpost Engineering Consultant Investment No 1 - Joint Stock Company

Address:
No.4, Lane 34, Nguyen Hong ward, Dong Da district, Ha Noi city.

Phone:
(+84) 24 3773 1910

Email:
info@tecco1.vn

Website:
www.tecco1.vn

Bridges - Tunnels

My Thuan 2 Bridge

About Project

Investor
Project Management Board 7 - Ministry of Transport.
Project location
Vinh Long City (Vinh Phuc) - Cai Be District (Tien Giang).
Implementation time
27/02/2020
Category
Bridges - Tunnels

My Thuan 2 Bridge is located on the expressway axis from Ho Chi Minh City to Can Tho City, connecting the two expressways Trung Luong - My Thuan and My Thuan - Can Tho, linking Vinh Long province and Tien Giang province. The bridge is part of the component project of the North - South Eastern Expressway phase 2017 - 2020. The My Thuan 2 Bridge project has a total length of 6.61 km, 350m upstream from the existing My Thuan Bridge. The total investment of the project is 5,003 billion VND.

The main bridge of My Thuan 2 Bridge has a length of about 1.9km, the bridge surface width is 28m, the scale is 6 lanes with a design speed of 80km/h. The bridge has a cable-stayed structure with two planes of cables, the main span is 350m with the main beam made of steel-reinforced concrete in the shape of the letter “Pi”. The 2 A-shaped towers are over 125m high, placed on a bored pile foundation with a diameter of 2.5m and a depth of up to 113m. My Thuan 2 Bridge is considered the first cable-stayed bridge entirely designed and constructed by Vietnamese engineers and workers, in which the construction of the bridge’s bored piles with the largest diameter and depth to date is considered a miracle of the Vietnamese bridge industry.